|
Timeline for Milestones |
|
Demolition - Spring |
| Staking
house - 7/7/09 |
| Clearing and
excavation - 7/21/09 - 7/28/09 |
|
Reconnect utilities - 8/03/09 |
| Footings -
8/03/09 |
| Foundation Walls -
8/04/09 - 8/7/09 |
| Rough-ins for
plumbing -
8/10/09 - 8/12/09 |
| Pour basement floor -
8/12/09 - 8/14/09 |
|
Finish basement misc. & patio - 8/20/09 - 8/21/09 |
|
Framing - 8/20/09 -
10/01/09 |
| Lightning Rods -
10/01/09 - 10/02/09 |
| Rough In Electrical -
10/01/09 - 2/05/10 |
| Rough In Plumbing -
11/02/09 - 1/12/10 |
| Duct Work - 10/23/09
- 11/13/09 |
| Pond Construction -
10/05/09 - 2/28/10 |
| Wrap Around Porch and
Decks - 10/01/09 - 10/23/09 |
|
Roofing - 10/12/09 - 10/23/09 |
| Windows & Doors -
10/19/09 -
11/06/09 |
| Stone -
11/23/09 - 12/30/09 |
| Exterior
siding, trim, veneers - 11/23/09 - 12/30/09 |
|
Insulation (upper) - 1/4/10 - 1/08/10 |
| Insulation (main) -
1/18/10 - 1/22/10 |
| Insulation (lower) -
2/08/10 - 2/10/10 |
| Drywall (upper) -
1/11/10 - 1/15/10 |
| Drywall (main) -
1/18/10 - 1/29/10 |
| Drywall (lower) -
3/01/10 - 3/10/10 |
| Drywall Finish
(upper) - 1/25/10 - 2/02/10 |
| Drywall Finish (main)
- 2/01/10 - 2/06/10 |
| Drywall Finish
(lower) - 3/10/10 - 3/19/10 |
| Priming upstairs -
2/2/10 - 2/3/10 |
| Painting upstairs - 2/03/10 -
2/05/10 |
| Priming Main Floor -
2/10/10 - 2/12/10 |
| Painting Main Floor - 2/15/10 -
2/17/10 |
| Priming Lower Level -
3/22/10 - 3/24/10 |
| Painting Lower Level -
3/24/10 -
3/26/10 |
| Interior trim
Upstairs - 2/22/10 -
3/03/10 |
| Interior trim Main
Floor - 3/03/10 -
3/09/10 |
| Interior trim Lower
level - 3/29/10 -
4/01/10 |
|
Cabinets - 3/08/10 -
3/12/10 |
| Appliances - 3/11/10 -
3/12/10 |
| Stairs - 3/08/10 -
3/12/10 |
| Countertops - 3/15/10
- 3/18/10 |
| Flooring Upstairs - 2/08/10 -
2/24/10 |
| Flooring Main Floor - 2/22/10 -
2/26/10 |
| Flooring Lower Level -
3/29/10 -
4/01/10 |
| Finishing plumbing -
3/02/10 - 3/10/10 |
| Finishing Mechanical
- 3/02/10 - 3/10/10 |
| Finishing Electrical
- 2/10/10 - 4/01/10 |
| Fire/Smoke/Security
System - 3/11/10 - 3/12/10 |
| Telephone/DSL -
3/03/10 |
| Clean Up Top Floor - 3/01/10 -
3/05/10 |
| Move in Top Floor - 3/05/10 -
3/07/10 |
| Clean Up Main Floor - 3/11/10 -
3/12/10 |
| Move in Main Floor - 3/12/10 -
3/14/10 |
| Clean Up Lower Level -
4/01/10 -
4/02/10 |
| Move in Lower Level -
4/03/10 -
4/04/10 |
| Porch
Columns and Railing - 3/22/10 - 3/26/10 |
| Driveway - Summer
2010 |
| Termite Protection -
After final grade |
| Landscaping - Summer
2010 |
| Pool - ? |