Timeline for Milestones
Demolition - Spring
Staking house - 7/7/09
Clearing and excavation - 7/21/09 - 7/28/09
Reconnect utilities - 8/03/09
Footings - 8/03/09
Foundation Walls - 8/04/09 - 8/7/09
Rough-ins for plumbing - 8/10/09 - 8/12/09
Pour basement floor - 8/12/09 - 8/14/09
Finish basement misc. & patio - 8/20/09 - 8/21/09
Framing - 8/20/09 - 10/01/09
Lightning Rods - 10/01/09 - 10/02/09
Rough In Electrical - 10/01/09 - 2/05/10
Rough In Plumbing - 11/02/09 - 1/12/10
Duct Work - 10/23/09 - 11/13/09
Pond Construction - 10/05/09 - 2/28/10
Wrap Around Porch and Decks - 10/01/09 - 10/23/09
Roofing - 10/12/09 - 10/23/09
Windows & Doors - 10/19/09 - 11/06/09
Stone - 11/23/09 - 12/30/09
Exterior siding, trim, veneers - 11/23/09 - 12/30/09
Insulation (upper) - 1/4/10 - 1/08/10
Insulation (main) -  1/18/10 - 1/22/10
Insulation (lower) -  2/08/10 - 2/10/10
Drywall (upper) - 1/11/10 - 1/15/10
Drywall (main) - 1/18/10 - 1/29/10
Drywall (lower) - 3/01/10 - 3/10/10
Drywall Finish (upper) - 1/25/10 - 2/02/10
Drywall Finish (main) - 2/01/10 -  2/06/10
Drywall Finish (lower) - 3/10/10 - 3/19/10
Priming upstairs - 2/2/10 - 2/3/10
Painting upstairs - 2/03/10 - 2/05/10
Priming Main Floor - 2/10/10 - 2/12/10
Painting Main Floor - 2/15/10 - 2/17/10
Priming Lower Level - 3/22/10 - 3/24/10
Painting Lower Level - 3/24/10 - 3/26/10
Interior trim Upstairs - 2/22/10 - 3/03/10
Interior trim Main Floor - 3/03/10 - 3/09/10
Interior trim Lower level - 3/29/10 - 4/01/10
Cabinets - 3/08/10 - 3/12/10
Appliances - 3/11/10 - 3/12/10
Stairs - 3/08/10 - 3/12/10
Countertops - 3/15/10 - 3/18/10
Flooring Upstairs - 2/08/10 - 2/24/10
Flooring Main Floor - 2/22/10 - 2/26/10
Flooring Lower Level - 3/29/10 - 4/01/10
Finishing plumbing - 3/02/10 - 3/10/10
Finishing Mechanical - 3/02/10 - 3/10/10
Finishing Electrical - 2/10/10 - 4/01/10
Fire/Smoke/Security System - 3/11/10 - 3/12/10
Telephone/DSL - 3/03/10
Clean Up Top Floor - 3/01/10 - 3/05/10
Move in Top Floor - 3/05/10 - 3/07/10
Clean Up Main Floor - 3/11/10 - 3/12/10
Move in Main Floor - 3/12/10 - 3/14/10
Clean Up Lower Level - 4/01/10 - 4/02/10
Move in Lower Level - 4/03/10 - 4/04/10
Porch Columns and Railing - 3/22/10 - 3/26/10
Driveway - Summer 2010
Termite Protection - After final grade
Landscaping - Summer 2010
Pool - ?

 

Okay totally not keeping up with the schedule. 

We slowed down the work at the end of March.  This allowed us to slow down the expenditures and also allowed the Amish boys to work on other projects. 

By Mid-March, we were able to start staying here, primitive camping style.  By April 1st we had one working toilet.   We officially moved in the last weekend in March. 

Here we are in Mid-May and we still only have ONE working toilet.  After using that one working toilet, you have to go to yet another bathroom to wash your hands.  If you want to take a shower, you have to go upstairs to yet another bathroom for that.  And if you want to take a bath, you have to use the main floor guest bathroom.  Geesh.

But the house is great.  We all love it. 

 