  Day 28 (work days since Framing started)
Sept. 30, 2009
  • Most of the windows & sliding glass doors were delivered.

  • Signs of activity in the Electrical Department

  • Temporary Stairs to the 2nd floor going in.

  Day 27
Sept. 29, 2009 Nothing new today.
  Day 26
Sept. 28, 2009
  • Wrap Around Porch started, along with the Old Porch Dog training program.

 

  • Dormer window in the F.R.O.G

 

  Day 25
Sept. 25, 2009
  • Medium Bronze 24 gauge standing seam metal roof ordered (on Monday actually)
  • Windows and doors have arrived at the lumber yard.  Probably a few more weeks before they are installed.
  Day 24
Sept. 24, 2009
  Day 23
Sept. 23, 2009
  Day 21 & 22
Sept. 21 & 22, 2009 No pictures, sorry.  Was in KC on Monday and had a Headache from H3LL on Tuesday, however work progressed.
  Day 20
Sept. 18, 2009  
  • Trench for electric

 

  • Skylight in upstairs bathroom

 

  • Upstairs Family Room

 

  • F.R.O.G.  (Finished Room Over Garage) This will be a Study for a few years, and then can be converted to a Bedroom or Playroom.

 

 

  Day 19
Sept. 17, 2009
  Day 18
Sept. 16, 2009 No new construction today.  The crew had a funeral to go to today. 
  • ADT came out and got all squared away.
  • Co-Mo installed a bigger transformer and new meter box.  The old meter was across the road with the barn meter. 
  Day 17
Sept. 15, 2009
  Day 16
Sept. 14, 2009
  • 2 Story-Foyer

 

  Day 15
Sept. 11, 2009
  • Electrical Supplies Arrive - 400 amp service

 

  • Trusses Arrive

 

 

  Day 14
Sept. 10, 2009

 

  • Lots of work went into getting the footings ready for the 2 story deck.

  Day 13
Sept. 9, 2009 No stairs mind you, I climbed a ladder to get these shots.  But once I got there, it was AWESOME!  The view was spectacular!  The breeze was very nice also.
  • View to the left, looking out from 2nd floor Great Room, which is actually 3 stories high on the back side.

  • View from the 2nd floor Great Room, again, this view is 3 stories high.  The pond will be in the draw where the first row of trees are.  There will also be a deck on this level.

  • Looking at the 2-Story Foyer from the 2nd floor balcony.

  • Looking at one of the Guest Rooms.  Probably the "pink" room for our grand-daughters and niece.

 

  Day 12
Sept. 8, 2009
  Day 11
Sept. 7, 2009 Another benefit of Amish builders, they work on Labor Day :-)

 

  • 2 Story foyer, looking up to the balcony

  Day 10
Sept. 4, 2009 Rain, Rain, Go Away......

 

Before the rain, a few more floor joists went up.  In the next picture, you can see that you can look through the front door, out the picture window on the back wall.

  Day 9
Sept. 3, 2009
  Day 8
Sept. 2, 2009

 

  • Trusses Ordered
  • Pressure tank set in house.  
  • Tray ceiling in the master bedroom.

  Day 7
Sept. 1, 2009
  • Windows and exterior doors ordered. 

 