Day 49 (work days since Framing started) |
|
Oct. 30, 2009 |
- Electrician and Plumber ready to start rocking and rolling on
Monday
- More Porch & House trim.

|
|
|
Day 48 |
|
Oct. 29, 2009 |
No pictures but work continued.
- Stairs were made from the garage into the mudroom.
- More Porch trim.
- Soffits were going in on the porch.
- More waterproof membrane.
|
|
|
Day 47 |
|
Oct. 28, 2009 |
- Pond construction at a halt due to rain.

- More Windows, More Waterproof Membrane
- More Sliding Glass Doors Installed
- Ridge Cap on Roof
 |
|
|
Day 46 |
|
Oct. 27, 2009 |
- Odds & Ends Sheeting and House wrap
- Waterproof membrane around windows


- Stone Ordered - Autumn Blend in a Canyon Ledgestone
- Siding Ordered - Autumn Taupe by Bristol Bay
|
|
|
Day 45 (since framing started) |
|
Oct. 26, 2009 |

- Copper Lightening Rods Installed

- Rumor has it the HVAC guy was there again today
|
|
|
Day 44 |
|
Oct. 23, 2009 |



- Ordered 12,000 pounds of flooring.
- Master Suite - Dark Couvertury Maple similar to an African
Wenge
- Main Level - Warm Nutmeg Pecan, similar to an Australian
Burlwood
- Upper Level - Dark Swiss Truffle Hickory
- Lower Level - Treehill Oak
|
|
|
Day 43 |
|
Oct. 22, 2009 |
More rain. Lots of little things were done on the inside, like
framing pocket doors, etc. Towards the end of the day, a few
windows started going in. Oh, and the 3rd story deck floor was
completed.

|
|
|
Day 42 |
|
Oct. 21, 2009 |

- Wading/Beach Area - This raised area behind the brush pile will
be an area of up to 2 ft deep for the smaller grandkids. Like
a kiddy pool section of the pond for wading, sitting in lounge
chairs, etc. Then it will taper into deeper water.
 |
|
|
Day 41 (since framing started) |
|
Oct. 20, 2009 |

- View from 3rd level on the back


- Since we are doing views, here is from the FROG window on the
south side towards the barn lot and tack barn

... and this is the FROG on the front side to the East


|
|
|
Day 40 |
|
Oct. 16, 2009 |




|
|
|
Day 39 |
|
Oct. 15, 2009 |
 |
|
|
Day 38 |
|
Oct. 14, 2009 |
- Pond progress. Hopefully it will dry out and he will come
back and make it a bit bigger :-)

 |
|
|
Day 37 (since framing started) |
|
Oct. 13, 2009 |
- Saw the electrician today
- Saw the pond digger today
- Saw something that resembles a front porch
 |
|
|
Day 36 |
|
Oct. 12, 2009 |
Wrap around continues to wrap on around

|
|
|
Day 35 |
|
Oct. 9, 2009 |

- Too muddy to go out back and get a picture of the upper Porch,
so here is a shot from up the road.
 |
|
|
Day 34 |
|
Oct. 8, 2009 |
Rain, Rain.... Work continued on the inside. |
|
|
Day 33 |
|
Oct. 7, 2009 |
- Pond finally under construction

 |
|
|
Day 32 |
|
Oct. 6, 2009 |
Work continued on Wrap Around Porch but no pictures |
|
|
Day 31 |
|
Oct. 5, 2009 |
- Wrap Around Porch Floor is Done


- New Pond starts tomorrow!

|
|
|
Day 30 |
|
Oct. 2, 2009 |
- Work continued on Wrap Around Porch



- I am pretty sure the dogs think we are building them a
great big dog house.
 |
|
|
Day 29 |
|
Oct. 1, 2009 |
- Work continued on Wrap Around Porch

- Temporary stairs to 2nd floor complete, but no pictures.
|