Click any thumbnail for a larger image.

  Day 49 (work days since Framing started)
Oct. 30, 2009
  • Electrician and Plumber ready to start rocking and rolling on Monday
  • More Porch & House trim.

  • FROG view into barn lot

  Day 48
Oct. 29, 2009 No pictures but work continued. 
  • Stairs were made from the garage into the mudroom.
  • More Porch trim.
  • Soffits were going in on the porch.
  • More waterproof membrane.
  Day 47
Oct. 28, 2009
  • Pond construction at a halt due to rain.

 

  • More Windows, More Waterproof Membrane
  • More Sliding Glass Doors Installed
  • Ridge Cap on Roof

  Day 46
Oct. 27, 2009
  • Odds & Ends Sheeting and House wrap
  • Waterproof membrane around windows

 

  • Trim Started on Porch

 

  • Stone Ordered - Autumn Blend in a Canyon Ledgestone
  • Siding Ordered - Autumn Taupe by Bristol Bay

 

  Day 45 (since framing started)
Oct. 26, 2009
  • More Windows

 

  • Copper Lightening Rods Installed

 

  • Rumor has it the HVAC guy was there again today

 

  Day 44
Oct. 23, 2009
  • More Roof

 

  • More Windows

 

  • More Roof & Windows

 

 

  • Ordered 12,000 pounds of flooring. 
    • Master Suite - Dark Couvertury Maple similar to an African Wenge
    • Main Level - Warm Nutmeg Pecan, similar to an Australian Burlwood
    • Upper Level - Dark Swiss Truffle Hickory
    • Lower Level - Treehill Oak

 

  Day 43
Oct. 22, 2009 More rain.  Lots of little things were done on the inside, like framing pocket doors, etc.  Towards the end of the day, a few windows started going in.  Oh, and the 3rd story deck floor was completed.
  • Windows

 

  • 3rd Story Deck

 

  Day 42
Oct. 21, 2009
  • Pond Progress

 

  • Wading/Beach Area - This raised area behind the brush pile will be an area of up to 2 ft deep for the smaller grandkids.  Like a kiddy pool section of the pond for wading, sitting in lounge chairs, etc.  Then it will taper into deeper water.

  Day 41 (since framing started)
Oct. 20, 2009
  • Pond Progress

 

  • View from 3rd level on the back

 

  • One View from back porch

 

  • Since we are doing views, here is from the FROG window on the south side towards the barn lot and tack barn

... and this is the FROG on the front side to the East

 

  • Roof Progress

 

  Day 40
Oct. 16, 2009
  •     Electrical Progress

  • Pond Progress

  • Rolling out the Roof

  • Roof Progress

 

  Day 39
Oct. 15, 2009
  Day 38
Oct. 14, 2009
  • Pond progress.  Hopefully it will dry out and he will come back and make it a bit bigger :-)

  • More Front Porch

  Day 37 (since framing started)
Oct. 13, 2009
  • Saw the electrician today
  • Saw the pond digger today
  • Saw something that resembles a front porch

  Day 36
Oct. 12, 2009 Wrap around continues to wrap on around

 

  Day 35
Oct. 9, 2009
  • Trench for Electric

  • Too muddy to go out back and get a picture of the upper Porch, so here is a shot from up the road.

  Day 34
Oct. 8, 2009 Rain, Rain....  Work continued on the inside.
  Day 33
Oct. 7, 2009
  • Pond finally under construction

  • Upper Deck Started

  Day 32
Oct. 6, 2009 Work continued on Wrap Around Porch but no pictures
  Day 31
Oct. 5, 2009
  • Wrap Around Porch Floor is Done

  • New Pond starts tomorrow!

 

  Day 30
Oct. 2, 2009
  • Work continued on Wrap Around Porch

  • View from Upper Level

  • View from Balcony

  • I am pretty sure the dogs think we are building them a great big dog house.

  Day 29
Oct. 1, 2009
  • Work continued on Wrap Around Porch

  • Temporary stairs to 2nd floor complete, but no pictures.