  Day 109 (Work days since Framing started + 15 work days for foundation)
Jan. 28, 2010
  • More Electrical.  Things progressing nicely on the lower level.
  • Fired up the furnace for the first time today.  It is temporary until we are ready for the Geothermal.
  • More Finish Drywall upstairs

  • More Hanging Drywall Downstairs. 
    • View into the kitchen

     

    • View from Kitchen towards Dining Area.   Opted against a formal dining and a formal living room.  This just made more sense for the way we would use the space.

     

    • View into the family room

 

  Day 108
Jan. 27, 2010
  • More Electrical
  • More Finish Drywall upstairs

  • More Hanging Drywall Downstairs.  This is shot from the dining room to the family room.

 

  Day 107
Jan. 26, 2010
  • Visited the cabinet maker today.  So far they look great!

The big piece is for the Frig & Freezer.  Cabinets across the top and the left are spice and oil racks, which will be next to the stove top. 

The other taller piece to the left of this piece, is the pantry that will be over by the coffee center.  I will also have a big pantry in the laundry room area.

This center piece is the bottom of the coffee center

 

 

This piece will have the stove top on the right side.  Above the left cabinets will be the microwave

 

Far left is the piece that will house the microwave with cabinets on top.

Next are the cabinets that will be to the right of the sink

Next is the piece that will have a cutting board and some storage baskets.  This is left of the sink.

 

This is the piece for the double oven.  Was suppose to have a warming drawer but it didn't get sent, so decided I didn't need it anyways, so more storage instead

 

Sitting on the top are the cabinets to the right of the sink.

Sitting on the bottom is the piece that will go above the coffee center.  The cut out on the bottom right corner is for the little frig that is for things like creamers etc.  I guess it is actually a wine frig.

 

This will be the island.  Then my camera was full (I forgot to put the sd card back in)

  • More Electrical - Furnaces are ready to fire up, probably in the morning.  Rough-in has moved to the lower level.  Yeah! the home stretch!
  • More Drywall

  Day 106
Jan. 25, 2010
  • More Electrical
    • This is like a communications hubb of some sort - satellite, internet, security camera, light switch to the Christmas lights is there also I think.  I don't really "get" this corner but David does, so it's okay.  This will be housed in the cabinetry around the fish tank.

    • More electrical in the kitchen area.

  • Downstairs electrical starting to show signs of progress

  • Fish Tank reframed. 

Foyer side

  This is the kitchen/pocket office side, which will be built into the cabinets.

  • Kitchen/pocket office

Built in desk side, opposite fish tank.  Round work table in the middle

  • Various views across the kitchen

  • Few taped and mudded (?) drywall shots.

 

  Day 105
Jan. 22, 2010
  • More Electrical - Good news though, the main floor is complete except for the media corner.  YEAH!!
  • Hanging drywall continued on main floor.
  • Finish drywall should start on Monday upstairs!  Yeah again!
  Day 104
Jan. 21, 2010
  • More Electrical
    • Kitchen power wall.  Right to left - Frig, Freezer, Stove, microwave, Double Oven.  Black tubing is RO tubing for the pot filler over the stove.

     

  • More Drywall

  • Kitchen Arch and Family Room Arch

  Day 103
Jan. 20, 2010
  • More Electrical
    • Pendants over Sink & Bar

     

     

  • Getting ready to fire up the furnace. 

 

 

 

  • Fireplace again, just because it is so pretty :-)

  • Lots of ceilings popped up all over the place
    • Laundry Room

     

    • Main Bathroom

     

    • Master Bath

     

    • Master Bedroom

     

    • Stairway going down

     

    • Archway into Family Room

  Day 102
Jan. 19, 2010
  • Electrical continued on main floor but about to wrap it up.  Electrician said that we will have 5 miles of wire in this house.
  • Some pics of the spray foam from the other day.

  • The blower was installed in the fireplace.

  • Blew some Cellulose into the Attic

  • Started drywall in the tray ceiling in the master bedroom

  Day 101
Jan. 18, 2010
  • Electrical continued.  Got the fireplace fired up today.  Yeah!  But it was turned off when I got there.

  • Lots of little things were done to get ready for drywall, probably on Wednesday.  Stairs were framed up.  Fish tank was framed up.  Pocket door for the Kitchen pocket office was framed up.

  • Few columns were wrapped on back porch

  Day 100
Jan. 15, 2010
  • Spray Foam is Complete on the Main Floor!  It looks AMAZING!
  • Electrical also continued.  Probably another week yet on the main floor before electrical is complete.  I think on the lower level, we will just use flashlights and lanterns.
  Day 99
Jan. 14, 2010
  • Fireplace electrical was wired.
  • Getting ready to spray foam main level tomorrow.

  • Drywall almost complete upstairs.  The hanging part that is.

  • Was so happy to see the dozer working this morning.  Then when I came back later, and as I walked around the edges, it really hit me hard.  This is the last step in the demolition, finish covering up the old house.  It was very very sad for me.

 

  Day 98
Jan. 13, 2010
  • Propane tank for Fireplace.  It will pretty much be concealed by the stairs landing.

  • More Electrical

 

 

 

 

  • More drywall upstairs

  Day 97
Jan. 12, 2010
  • More ROCKING upstairs.  Might be complete tomorrow?
    • Braydon's Room

     

    • F.R.O.G. Study

     

    • Bathroom w/ W/D around the corner

     

    • Steam Shower in Bathroom

     

    • Upstairs Electrical

     

    • Kitchenette/Bar off Family Room

     

    • View down the Hall from Family Room.  Kitchenette on right, Bathroom on Right, Guest Room on Left, step down into F.R.O.G. with closets on left, mechanical room on right, then the rest is the study.

     

    • Most of the Interior Lights.  Still have to figure out where I put about 6 of them, and still need to buy half a dozen or so.

     

    • Most of the Exterior Lights

     

  • Morning Sunshine

  • Rough-In Plumbing Complete
  • Rough-In Electrical Continues on Main Floor
  Day 96
Jan. 11, 2010
  • Rough in electrical continued on main floor.
  • Spray foam in the upstairs family room, the 2 story foyer and north wall.  It looks FANTABULOUS!  So nice and toasty upstairs.

  • Things are Rocking in the F.R.O.G!!!  This is the reading nook.

  • This is one of the doors that was ordered to see how the closet door switch was going to work inside the door jam.  Theory is, door opens, light turns on.  Door closes, light goes off... Interesting concept.

  Day 92 - 95
Jan. 5 - 8, 2010
  • Rough in electrical continued on main floor
  • Finished the pink stuff on upper level
  Day 91
Jan. 4, 2010
  • Rough in plumbing continued on lower level and outside spigots
  • Rough in electrical continued on main floor and extra CAT 5 lines upstairs
  • Insulation in FROG
  • Finished ceiling and hanging drywall in garage

 

 