  Day 140 - 141 (Work days since Framing started + 15 work days for foundation)
Mar. 10 - 11, 2010 
  • More Electrical Finishing Stuff
  • More Railing
  • More Trim Work
  • but More Kitchen Work is the only thing I have pictures of

  • Coffee Center - complete with it's own RO sink and Creamer Frig

  • The Power Wall - Double Oven, Microwave, and still to come the Range Top, Range Hood, Pot Filler w/RO water, Full Freezer w/RO icemaker, Full Refrigerator, and all in Stainless Steel

  • Sink Counter - Home of the 42" Empire Everest Double Bowl Farm Sink and Dishwasher

The Pocket Office

  • See-Thru Fish tank on the Left

  • Desk on the Right, with a round table in the middle for extra work space

And the reason why I call it a Pocket Office.... introducing the new Pocket Doors.  TA DA!!

 

  Day 138 - 139
Mar. 8 - 9, 2010  The rail on the back porch is friggin AWESOME!

 

The porch ceiling fans are way kewl also.

 

Kitchen cabinets going in

Top of desk in pocket office off the kitchen

  Top of Fish Tank in the pocket office.  Other side of fish tank will be framed in the foyer

 

Upstairs bathroom

 

LED nightlights.  Sweet

 

Switch plates going in.  Sweet

 

  Day 137
Mar. 5, 2010 Geothermal stuff

Main System

Upstairs Unit

 

Fireplace finished except for mantle

 

Most of the porch lanterns are on

 

Closetmaid system in upstairs closet

 

Braydon putting his desk together

 

  Day 136
Mar. 4, 2010 No pics but the Geothermal is running upstairs.

More floorboard trim on the main floor

More drywall on the lower level.

Fireplace is almost completely stoned.

  Day 133 - 135
Mar. 1 - 3, 2010 Little action in the Geothermal Department

Last of the main floor lights

Fireplace is getting stoned

Doors are hung on main floor

Drywall started on lower level

Upstairs is pretty much finished.  Except for electric covers, a few dummy door knobs, and the bathroom, it is ready to go.

 

 

 